Concrete Calculator: How to Estimate Volume for Any Project

Quick Answer: Concrete volume in cubic yards = (Length × Width × Depth in feet) / 27. A 10 × 10 ft slab, 4 inches thick = (10 × 10 × 0.333) / 27 = 1.23 cubic yards. Always add 5–10% for waste. At ~$150/yard delivered, that slab costs roughly $200–$210 for concrete alone.

Ordering concrete is one of those tasks where precision pays off immediately. Order too little and the truck leaves before you finish — now you are scrambling for bags from the hardware store to fill the last corner. Order too much and you are paying for concrete with nowhere to put it. Both scenarios cost money and time. Here is how to get the number right.

The Basic Concrete Volume Formula

Volume (cubic yards) = Length (ft) × Width (ft) × Depth (ft) / 27

Why divide by 27? Because 1 cubic yard = 3 ft × 3 ft × 3 ft = 27 cubic feet. Ready-mix concrete is sold by the cubic yard in the US (or cubic meter in metric countries).

Metric Version

Volume (m³) = Length (m) × Width (m) × Depth (m)

Volume Formulas by Shape

ShapeFormulaCommon Use
Rectangle/SlabL × W × D / 27Driveways, patios, garage floors
Circular slabπ × r² × D / 27Round patios, fire pit pads
Wall/FootingL × H × W / 27Foundation walls, stem walls
Column/Pierπ × r² × H / 27Deck piers, Sonotube footings
Trench footingL × W × D / 27Continuous footings, grade beams
StepsSum of individual step volumesPorch steps, stairways

Worked Examples

Example 1: Driveway Slab

A driveway 20 ft long, 12 ft wide, 5 inches thick:

Volume = 20 × 12 × (5/12) / 27 = 20 × 12 × 0.417 / 27 = 100 / 27 = 3.70 cubic yards

With 10% waste: 3.70 × 1.10 = 4.07 → order 4.25 yards

Example 2: Sonotube Footings

8 footings, each 12 inch diameter (r = 0.5 ft), 48 inches deep (4 ft):

Volume per footing = π × 0.5² × 4 / 27 = 3.14 × 0.25 × 4 / 27 = 0.116 cubic yards

Total = 8 × 0.116 = 0.93 cubic yards

With waste: approximately 1.0 cubic yard

Example 3: Foundation Wall

A foundation wall 80 ft perimeter, 8 ft tall, 8 inches wide:

Volume = 80 × 8 × (8/12) / 27 = 80 × 8 × 0.667 / 27 = 426.7 / 27 = 15.8 cubic yards

With 5% waste: 16.6 → order 17 yards

Example 4: Concrete Steps

3 steps, each 4 ft wide, 7.5 inch rise, 11 inch run, plus a 4 ft × 4 ft top landing 4 inches thick:

Waste Factor Guide

Project TypeWaste FactorWhy
Flat slab on grade (formed)5–7%Minor subgrade unevenness
Slab on grade (unformed edge)10–15%Edges spread without forms
Foundation walls3–5%Well-formed, minimal waste
Trench footings (earth-formed)10–20%Irregular trench walls absorb concrete
Pumped concreteAdd 3–5%Line priming and residual in the pump
Pro Tip: When ordering from a ready-mix plant, round up to the nearest quarter or half yard. Trucks deliver in increments, and a short-load fee ($50–$100) applies if you order less than the truck's minimum (often 3–4 yards). Sometimes paying for an extra half yard is cheaper than the short-load charge.

Ready-Mix vs. Bagged Concrete

FactorReady-Mix (truck delivery)Bagged (60/80 lb bags)
Best forOver 1 cubic yardUnder 0.5 cubic yards
Cost per yard$130–$200$250–$400 (bag equivalent)
Mix consistencyExcellent (plant-batched)Varies (hand or machine mixed)
LaborMinimal — truck poursSignificant — mixing bag by bag
TimingMust pour all at onceWork at your own pace

Bags per Cubic Yard

At $5–$7 per 80 lb bag, one cubic yard from bags costs $210–$294 in materials alone — before your labor mixing them. Ready-mix is almost always cheaper above 0.5 yards.

Concrete Cost Estimating

Cost ComponentTypical Range
Ready-mix concrete (per yard)$130–$200
Delivery charge$0–$50 (often included within 20 miles)
Short-load fee (<minimum)$50–$100
Saturday/overtime pour$50–$150 surcharge
Pump truck (if needed)$150–$300/hour (2-hour minimum typical)
Fiber reinforcement (per yard)$5–$10
High-strength upgrade (4000+ PSI)$10–$20/yard over standard 3000 PSI

Estimate your concrete volume with our Concrete Calculator and plan foundation dimensions with the Footing Calculator.

Frequently Asked Questions

How thick should a concrete slab be?

Residential patios and walkways: 4 inches. Garage floors and driveways for cars: 4-5 inches. Driveways for heavy vehicles (RVs, trucks): 5-6 inches. The extra inch from 4" to 5" adds only about 25% more concrete but roughly doubles the slab's load capacity.

How many bags of concrete make a cubic yard?

About 42 bags of 80-lb concrete or 56 bags of 60-lb concrete per cubic yard. Each 80-lb bag yields approximately 0.6 cubic feet of mixed concrete (0.022 cubic yards).

What PSI concrete should I order?

3,000 PSI: walkways, patios, non-structural slabs. 3,500 PSI: driveways, garage floors. 4,000 PSI: foundations, structural columns, commercial floors. 4,500+ PSI: freeze-thaw exposure, bridge decks, special structural applications. Most residential work uses 3,000-3,500 PSI.

How long does it take concrete to cure?

Concrete reaches about 70% strength in 7 days and 99% in 28 days (at 70°F). You can walk on it after 24-48 hours. Drive on a driveway after 7 days. Full cure for maximum strength and durability: 28 days. Keep it moist for the first 7 days (curing compound or wet burlap) for best results.

What is the maximum time between concrete truck arrival and finishing?

Ready-mix should be placed within 60-90 minutes of batching (or 300 drum revolutions). In hot weather, this window shrinks. Tell the dispatch your pour rate so they time truck arrivals to avoid delays. Retarders can extend workability in extreme heat.