How to Calculate Concrete Needed

Concrete formula: Length (ft) × Width (ft) × Thickness (ft) ÷ 27 = cubic yards of concrete. For a 10×10 ft slab at 4 inches thick: 10 × 10 × 0.33 ÷ 27 = 1.23 cubic yards. Always add 10% for waste.

The Concrete Volume Formula

Concrete is measured and ordered in cubic yards. The formula for a rectangular pour is:

Volume (cu yd) = Length (ft) × Width (ft) × Depth (ft) ÷ 27

Divide by 27 because there are 27 cubic feet in one cubic yard (3 ft × 3 ft × 3 ft = 27).

Step-by-Step Calculation

  1. Measure the length and width of the area in feet.
  2. Convert thickness to feet. 4 inches = 4÷12 = 0.333 ft. 6 inches = 0.5 ft.
  3. Multiply: L × W × D. This gives cubic feet.
  4. Divide by 27 to convert to cubic yards.
  5. Add 10% for waste and overfill.

Quick Reference: Concrete for Common Projects

ProjectDimensionsThicknessCubic Yards
Small patio10 × 10 ft4 in1.2 yd³
Standard driveway10 × 20 ft4 in2.5 yd³
Two-car driveway20 × 40 ft4 in10 yd³
Garage floor20 × 20 ft4 in5 yd³
Sidewalk (50 ft)50 × 4 ft4 in2.5 yd³
House foundation (perimeter)varies8 inCalculate per section

Converting Cubic Yards to Bags

If you're doing a small project with bags instead of ready-mix delivery:

For a 10×10 patio at 4" thick (1.2 cubic yards): 1.2 × 45 = 54 bags of 80-lb concrete (plus 10% waste = 60 bags).

Footing Calculations

For a strip footing or column footing, calculate the volume the same way — length × width × height. For a round column footing, use: π × radius² × depth.

Example: Round footing 18" diameter, 24" deep: 3.14159 × (0.75)² × 2 = 3.53 cubic feet = 0.13 cubic yards.

Ordering Concrete

Ready-mix concrete is typically ordered in 0.5 cubic yard increments. Minimum orders are usually 1 yard. Most trucks deliver up to 10 yards per load.

Use our Concrete Calculator to get an exact estimate for your project, or our Footing Calculator for foundation work.

Frequently Asked Questions

How do I calculate cubic yards of concrete?

Length (ft) × Width (ft) × Depth (ft) ÷ 27. For a 10×10 ft slab at 4 inches thick: 10 × 10 × 0.333 ÷ 27 = 1.23 cubic yards.

How much concrete do I need for a 10×10 slab?

A 10×10 ft slab at 4 inches thick requires 1.23 cubic yards of concrete. With 10% waste, order 1.35 cubic yards. At 6 inches thick, you need 1.85 cubic yards.

How many 80-lb bags of concrete make a yard?

45 bags of 80-lb premixed concrete equals one cubic yard. 60-lb bags require 60 bags per cubic yard.

Should I add 10% extra when ordering concrete?

Yes. Always order 10% more than your calculated volume to account for waste, spillage, slight variations in form depth, and the fact that you can't return partial loads.

What is the standard concrete thickness for a driveway?

Residential driveways are typically 4 inches thick for passenger cars. For vehicles over 5,000 lbs or heavy truck traffic, 6 inches is recommended.